The work continues to progress ahead of schedule, and if it continues all works should be completed well before school starts in September.

All the underground servicing piping is completed, except for the Bluevale intersection and the School’s water service scheduled for connection Wednesday evening. The Contractor will be starting to build the road base back up. Tomorrow they will be working close to the Bluevale intersection to excavate and bring in Granular B gravel for the road base. We have requested any gravel deliveries happen well outside of the bell times and that they stay back from the Neilson crossing an additional 5 metres and ensure there is someone available for crossing students/pedestrians safely as required. Our inspector Barry Vlasman (who is excellent) will be over seeing all this work.